Development Timeline
Preliminary Plat Application 4/15/2004
Request for Annexation into City 4/15/2004
Meeting with Fish & Game and Army Corps of Engineers On-site to Establish Blue Heron Habitat 10/21/2005
Application for Planned Unit Development 1/27/2005
City Council Hearing 3/7/2006
City Plan Approval  
phase 1 3/28/2006
phase 2 8/1/2006
ACHD Plan Approval  
phase 1 Apr-06
phase 2 Aug-06
phase 3  
Start of Construction  
phase 1 May-06
phase 2 Aug-06
phase 3 Jan-06
phase 4 Dec-06
Completion of Infrastructure  
phase 1 Mar-07
phase 2 In Progress
phase 3 In Progress
phase 4 In Progress
Submit Final Plat Application 3/6/2006
Recorded Plat 1/22/2007
phase 1 1/22/2007
phase 2 Est. 5/8/07
phase 3  
First Home Started 1/24/2007
First Home Sale 2/1/2007
CC&R's - Recorded 3/2/2007
Start of Clubhouse Construction 3/19/2007
Start of Pool Approx. 6/1/07
Ponds Dec-06
Start of Commercial Est. May 07